500 km out of 593.94 km Ganga Expressway in Uttar Pradesh has undergone clearing

As of December 27, 500 km out of the entire 593.94 km of the Ganga Expressway in Uttar Pradesh has undergone clearing and grubbing work, signalling a progress in the preparation work.

84.11 percent of the civil construction work and 7.3% of the earthwork on the motorway have been finished, according to the daily status report provided by the Uttar Pradesh Expressways Industrial Development Authority (UPEIDA).

Clearing and grubbing refer to the process of preparing the construction site. Trees are felled during the clearance phase. The term “grubbing” describes the clearing and removal of organic waste and stumps.

On December 18, 2021, Prime Minister Narendra Modi opened the six-lane motorway connecting Meerut and Prayagraj in Shahjahanpur, Uttar Pradesh.

The ambitious project to build an expressway connecting eastern and western parts of Uttar Pradesh has been in the pipeline since 2007 and was revived in 2019.

Site Moved. Visit our New Website

We have moved this news site from this URL to https://www.newprojectstracker.com/capex-news .

Visit this site for regular updates

Buy Latest Research Reports

Jayaparakash Sampath

Founder & CEO at NPT Research Information Services

Related Posts